NISTA red-flags cladding plan as 1,923 blocks still wait

The government’s cladding remediation programme has been red-flagged by the National Infrastructure and Service Transformation Authority, with 1,923 identified buildings still not on site as of March 2026.

NISTA said the Remediation Acceleration Plan now faces “risks to pace and affordability”, downgrading confidence in delivery as higher social housing volumes, Building Safety Regulator constraints and construction cost inflation weigh on progress.

For landlords with leasehold flats or blocks caught in remediation schemes, the warning matters now because delays keep holding up sales, refinancing and long-term planning. It also raises fresh doubt over whether ministers can move unsafe buildings through the system at the speed they have promised.

1,531 unsafe-cladding cases complete but backlog remains

According to NISTA’s 2025-26 Major Projects Annual Report, 4,322 buildings over 11 metres had been identified with unsafe cladding by the end of March. Work had started on 2,399 of them, including 1,531 completed schemes and 868 live on site, but another 1,923 had still not started on site.

The watchdog said delivering the programme against its existing business-case assumptions would be challenging. It pointed to pressure from the pace of delivery, rising costs, Building Safety Regulator constraints and the need to speed up developer-led works.

Becky Wood, chief executive of NISTA, said the ratings were intended as an early warning so departments could identify risks sooner and deal with pressure before it became more serious.

This follows Residential Landlord’s earlier coverage of high service charges leaving many flats harder to finance, and Residential Landlord’s report on ministers trying to cut failed sales. The latest red flag shows why flat landlords remain exposed to building-safety delays even when wider market reform is moving ahead.

There is some progress in the numbers. NISTA noted targeted action to speed up Gateway 2 approvals, while the Building Safety Levy is due to launch in October to help fund work on mid-rise blocks. But landlords should be careful not to over-read that progress. A programme can move forward on paper while individual buildings remain stuck for months on approvals, funding or contractor capacity.

The authority’s 2025-26 Major Projects Annual Report says the current timetable is under real strain. That matters for investors holding flats in affected blocks, because uncertainty still feeds into valuations, mortgage options and exit timing.

Flat landlords still face valuation and exit pressure

For investors, the practical problem is that cladding delay is not just a safety issue. It can freeze disposals, complicate refinancing and drag down demand from buyers who do not want open-ended risk around future works, service charges or lender requirements.

If the government cannot accelerate the slowest cases, landlords may find that newly announced funding and policy changes improve sentiment without fixing the real bottleneck. The issue is no longer whether the state accepts the scale of the problem. It is whether the delivery system can clear the backlog before more owners give up waiting.

Opinion

A red flag from the government’s own infrastructure watchdog should not be brushed aside as routine project management language. Flat landlords have heard promises on cladding for years, but nearly 2,000 identified buildings still waiting to start work is the number that matters. Until that backlog starts falling faster, confidence in this part of the market will stay fragile.